1. The steel platform should be equipped with a limit plate.
2. The resting point and the upper tension point of the steel platform must be located on the building, and shall not be set on construction facilities such as scaffolding, and the supporting system shall not be connected with the scaffolding.
3. The concrete beam slab at the resting point of the steel platform should be embedded and connected with the bolts of the platform.
4. The horizontal angle between the wire rope and the platform should be 45 degrees to 60 degrees.
5. The tensile strength of the beams and columns of the tensile nodes on the upper part of the steel platform should be checked to ensure the safety of the building and the platform.
6. When using a steel platform, a snap ring should be used, and the hook should not be directly hooked to the platform ring.
7. When installing the steel platform, the steel wire rope should be fastened with a special hook. When other methods are used, there should be no less than 3 buckles. The wire rope around the acute angle of the building should be lined with cushions, and the outer opening of the steel platform should be slightly higher. on the inside.
8. The left and right sides of the steel platform must be equipped with fixed protective railings and a dense mesh safety net.